New Distribution Centre - Bedford

BEDFORD

Project: Turnkey design, build and fit out of a new food distribution warehouse

Sector: Commercial

Scope: The design and installation of a new distribution facility for a. major UK food distributor in its entirety, transforming a new build warehousing unit into a central distribution hub from concept to completion allowing for the installation of new offices and welfare facilities, an upgrade to the previously installed electrical, mechanical and fire alarm systems, data and I.T systems and the creation of a bespoke catering kitchen to the client’s own specification.

Design and installation of external commercial charging points and barrier systems to the car park and the construction of concrete foundation pads left ready to receive the installation of new col store chiller units.

Upon completion, Paradigm Interiors were also invited to carry out the dilapidation works to the clients existing site, all completed to predetermined timescales and within the allocated budget.

Budget: New distribution centre   £450k

Duration: 30 Weeks

Budget: Dilapidations   £125k

Duration: 8 Weeks